Faculty Advisor

Albano, Leonard D.

Faculty Advisor

FitzPatrick, Malcolm S.

Abstract

Most urban developments are faced with the problem of dealing with stormwater runoff, including treatment and recharge. The Lowland Industrial Park in Holliston, MA, was used as a typical site to evaluate hydrology and recharge potential using map overlays, the TR-55 methodology, an investigation of the existing drainage infrastructure, and the design of a stormwater treatment and recharge system. This project was developed in conjunction with the Charles River Watershed Association and can be used as a model for similarly developed areas. The final recommendations represent an effective stormwater management plan for Lowland Industrial Park.

Publisher

Worcester Polytechnic Institute

Date Accepted

January 2001

Major

Civil Engineering

Project Type

Major Qualifying Project

Accessibility

Restricted-WPI community only

Advisor Department

Civil and Environmental Engineering

Share